ANNO Facade Lighting Engineering project implementation process is scientific and standardized: from construction preparation, pipeline laying to lamp installation, distribution box configuration and other basic operations, followed by lightning protection and grounding construction, system debugging and weak current detection to ensure reliable operation, and finally achieve customized presentation of lighting effects. The whole process strictly controls the construction quality, while meeting personalized needs to ensure high-quality project delivery.
Construction procedure: Construction preparation → Prefabrication and processing of pipe bending → Determination of box position → Fixing of box and box → Pipe connection → Expansion joint treatment → Grounding treatment
Construction procedure: Threading in pipes → Threading of belt wires → Cleaning of pipes → Laying and breaking wires → Binding of wires and belt wires → Checking pipe openings and threading → Wire connection → Wire wrapping → Line inspection and insulation telemetry
Installation procedure: Unpacking inspection → Lighting positioning → Bracket installation → Lighting installation → Lighting wiring installation → Adjustment of projection angle
Construction procedure: Equipment unpacking inspection → Cabinet fixing → Primary wiring → Secondary wiring → Test adjustment → Power transmission and operation
Construction procedure: Construction preparation → Installation of grounding electrodes → Installation of down conductors → Connection to lightning protection network → Grounding resistance test
Debugging process: dust cleaning → prepare tester, insulating shoes, gloves, fire extinguisher → cut off the incoming power supply of all lighting distribution boxes → disconnect the distribution box for switching → connect temporary power supply and power supply → open the 1-circuit switch in the box → check whether the lamp is normal → gradually open all the circuit switches of the distribution box to check whether the lamp is running normally → use the same method as above to debug the remaining distribution boxes → after the regional debugging is completed, the overall power supply debugging operation → cut off the lighting distribution box control switch/lock the distribution room → run the main line without load for 24 hours → check the problem and solve it
Debugging process: debugging preparation → check the equipment installation and connection → plan the entire system → system debugging